Carson, California
Los Angeles Refinery Integration and Compliance (LARIC)
Client / Owner
Andeavor (formerly Tesoro)
Architect / Engineer
Fluor
Market
Process
Oil, Gas & Chemicals
Company
Graycor Industrial
Project Scope
Andeavor (formerly Tesoro) awarded Graycor Industrial Constructors a project as part of the Los Angeles Refinery Integration and Compliance (LARIC) modernization. Graycor Industrial’s work at the Carson, California, refinery marked a geographic expansion of its western footprint as well as its first time working for San Antonio, Texas-based Andeavor.
In July 2017, Graycor’s team mobilized to the Carson refinery and began work on the multimillion-dollar project which called for above-ground mechanical, piping, structural steel, demolition, electrical and instrumentation. The project was completed in March 2018.
Graycor’s scope included mechanical work as well as self-performance of some of the structural steel erection.
The team worked in three areas throughout the refinery: Carson Light Hydro Unit (CLHU), Carson No. 51 Vacuum Unit and Dehex (CVAC).
Major subcontracted work included electrical, scaffolding, insulation, painting and fireproofing.
Andeavor plans to invest $460 million to connect, further integrate and upgrade the adjacent Carson and Wilmington facilities. When completed, the combined Los Angeles Refinery will run more cleanly and efficiently.