San Francisco Airport Marriott Waterfront

San Francisco, Calif.

Client / Owner
Host Hotels and Resorts, Inc.
Architect / Engineer
Houston/Tyner Architects, Inc.
Market
Living + Lodging
Company
Graycor Construction

Project Scope

CGraycor completed a renovation project at the San Francisco Airport Marriott for Host Hotels and Resorts, Inc. The project, with a tight schedule and long hours, included renovation of the ballroom, assembly areas and public restrooms. The 25,000-square-foot ballroom was fast-tracked over six weeks during the peak holiday season. In order to stay on schedule, Graycor had to coordinate long lead items such as the light fixtures, millwork and door hardware. One significant challenge on the project were the owner-supplied chandeliers, which required quick and detailed installation in a short amount of time. Graycor completed the project on schedule, which allowed the hotel to keep previously booked renovations.