Boiler System Replacement
Dresden Station Control Room - Steam Boiler System Replacement
Client:
Dresden Generating StationProject scope:
Graycor Industrial replaced two 40,000-lb./hr heating boilers inside the Dresden Station protected area. Scope of work for this project also included all boiler and related equipment installation, a new stack, and auxiliary work. All work peformed for this project required "hot area" precautions.Browse projects by:
-